Project Detail

Project Detail

Project Name SPACE 21
Road LOR 21 GEYLANG
Location Local
District D14 - GEYLANG, EUNOS
Region Central Region
Broad Region Rest of Central Region (RCR)
Country Singapore
Category INDUSTRIAL
Expected Top 30 JUNE 2023
Expected Date Legal Completion 30 JUNE 2023
Tenure FREEHOLD
Land Size Area 15,364 sqft
Site Use Industrial
Mukim Lot No MK24-03957N
No Lift Lobbies 1 service lift, 1 passage lift
Total No Units 20 units (included one industrial canteen)
Addresses

  • 51 Lorong 21 Geylang Singapore 388466

You Are Most Welcome To

Book An Appointment for a Viewing of the Industrial Units at Space 21.  Let us explain why this is a Rare and Absolute Freehold Industrial Space Ownership.  In addition, get to enjoy VVIP Discount (Limited Time), and Guaranteed with Best Price Possible

OR

Fill up the form and get a copy of Space 21 Prices, E-Brochure and Latest Updates!

Space 21 Contact Us

  • This field is for validation purposes and should be left unchanged.

Building Specifications

Foundation
Generally reinforced concrete bored pile foundation

Structure
Cast in-Situ reinforced concrete frame

Roof
Reinforced concrete flat Rrof with appropriate waterproofing and insulation system and metal roofing over the factory units

Internal Wall
Generally lightweight concrete panel/block wall/ impact-resistant drywall with skim coat and emulsion paint
Homogenous wall tiles to toilets to 2400mm height and emulsion paint on skim coat above
2400mm height.
Homogeneous wall tile to lift lobbies

External Wall
Reinforced concrete/lightweight concrete panel/block wall where appropriate with skim coat and painting.

Floor Loading
Factory floor:7.5kN/m2
Mezzanine floor: 3.0KN/m2

Floor to Floor Height
1st storey: 5.185m
2nd to 5th storey: 7.0m

Windows
Aluminum-framed glazing / Aluminum louvres/ Aluminum-framed window system with glazing

Doors
Approved timber door with quality lockset to main entrance of units
Slide and fold PVC door with lockset to toilets
Glazing at 1st storey where applicable

Ceiling
Units: Skim coat and emulsion paint finish
Toilets: Suspended ceiling
Common areas: Plaster and emulsion paint finish/suspended ceiling

Floor Finishes
Generally power float concrete floor to all areas except lift lobbies and toilets
Homogeneous tile to lift lobbies, common corridor and toilets

Electrical Supply
60A 3Phase Isolator provided to individual unit
KWH Meter located inside the common electrical riser

Gas Supply
There is no gas provision to the building

Fire Protection
Sprinkler, fire alarm , dry risers, hose reel systems, fire extinguishers, voice communication systems, emergency lighting, exit signs are provided in compliance with statutory requirements

Air Conditioning/Mechanical
Provision of air conditioning to lift lobbies
Mechanical ventilation in compliance to authority requirements for designated areas

Lifts
1 service lift and 1 passenger/fire lift

Plumbing and Sanitary
Accessible toilets in compliance with statutory requirements
Units: 1 water closet; 1 wall-hung wash basin with mixer tap; 1 bidet spray; 1 toilet paper holder
Sanitary and plumbing installation systems are provided in compliance with Government Authority requirements
Piping works from meter compartment to unit with cap off at unit entrance

Telecommunication
Infrastructure( cable tray and/or trunking and/or conduit) for telecommunication is provided in compliance with IDA requirements

Lightning Protection
Lightning Protection System provided in compliance with statutory requirements

PA System
Voice Communication system provided in compliance with statutory requirements;
2 speakers provided per individual unit;

Loading Bays
2 loading bays at 1st storey

Car Parks
6 car spaces inclusive of accessible lot for disabled at 1st storey

Refuse Disposal
One common bin point at 1st storey